Possession Linked Payment Plan |
At the time of Booking |
5% of BSP |
Within 3 Months from date of booking |
5% of BSP |
Within 6 Months from dateof booking |
10% of BSP + 20% of PLC (TPR Rs. 50 Per Sq.Ft.) |
Within 12 Months from date of booking or Start of Excavation work |
10% of BSP + 10% of PLC (TPR Rs. 50 Per Sq.Ft.) |
Within 18 Months from date of booking |
10% of BSP + 10% of PLC (TPR Rs. 100 Per Sq.Ft.) |
On casting of top floor roof slab |
30% of BSP + 20% of PLC (TPR Rs. 100 Per Sq.Ft.) |
On offer of Possession |
30% of BSP + 40% of PLC + 100% of EDC / IDC + IFMSD + Electric Meter Installation Charges + Gas Pipeline Charges + STP Charges + Stamp Duty & Registration Charges + Escalation in Construction Cost (if any) |
Construction Linked Payment Plan |
At the time of Booking |
5% of BSP |
Within 3 Months of Booking |
5% of BSP |
Within 6 Months of Booking |
10% of BSP |
Start of Foundation |
10% of (BSP + PLC) |
Start of Foundation |
5% of BSP + 10% of PLC |
Casting of Stilt Floor Roof Slab |
5% of BSP + 10% of PLC |
Casting of Level One Floor Roof Slab |
5% of BSP + 10% of PLC |
Casting of Level Two Floor Roff Slab |
5% of BSP + 10% of PLC |
Casting of Top Floor Roof Slab |
5% of BSP + 10% of PLC |
Start of Masonary Work inside the unit |
5% of BSP + 10% of PLC |
Start of Painting Work inside the unit |
10% of BSP + 10% of PLC |
Start of Flooring Work inside the unit |
10% of BSP + 10% of PLC |
On offer of Possession |
20% of BSP + 10% of PLC + 100% of EDC / IDC + IFMSD + Electric Meter Installation Charges + Gas Pipeline Charges + STP Charges + Stamp Duty & Registration Charges + Escalation in Construction Cost (if any) |
Note: -
- Unit Size may vary +/†10%
- Prices subject to revision at the sole discretion of the Company
- Please ask for the availability before booking
- Service tax shall be applicable as per rates notified by the government and is subject to change and payable along with respective installment and is mandatory
- The above cost is inclusive of 1 Car Park for 2BHK units & 2 Car Park for 3BHK & above sized units.
- EDC/IDC are pro - rated per unit as applicable, any revision would be charged on pro rata basis from the customer.
- Govt. Charges Electricity, water and sanitary are to be asscertained and payable by the customer at the time
- As per Govt Rules service tax is paid on each installment.
- Registration and stamp duty charges shall be payable along with final installment, as applicable
- In case of escalation in construction cost, resulting from increase in cost of construction inputs like steel, cement, labour etc, BSP shall be revised at the sole discretion of the Company.
|